Design Services for the Construction of the Proposed Facility:
Preparing detailed plans and designs for the upgrading works, including plans for increasing the primary treatment capacity and adding secondary treatment for both plants
Adding sludge dewatering unit for the Eastern plant
Preparing the tender documents of the EPC tender for both plants
Procurement Support Services:
Conducting pre-construction procurement support activities by monitoring the Contractor’s pre-qualification process, review of tender documents, and bid evaluation results
Supervision of implementation for the Eastern WWTP
Review & approval of all pre-construction deliverables and submittals
Supervising operation & maintenance activities for the Eastern WWTP